Progress of the Campus Network Major Upgrade
We are happy to report that, as a result of intensive work this summer, Phases II and III of the Campus Network Major Upgrade are now near completion. The network points installed all over the Main Campus, the Sassoon Rd. Campus and the Prince Philip Dental Hospital are being put into operation. They are expected to be fully in service by end of October. We are also working closely with the Queen Mary Hospital administration to start the installation for the QMH compound soon. As cable installation in the Professorial Block and the New Clinical Building has to go in tandem with their ceiling replacement project, we anticipate the network points on the QMH premises to be operating by early 1999.
Up to the present, the completion status and schedule are as follows
:
| Completed by late August: | ||
|
|
||
| Completed by early September: | Completed by mid-September: | Completed by late-September: |
| Completed by mid-October: | ||
| To be completed by late October:
To be completed by early 1999 : |
||
|
|
||